title: "15 Billion UAH Debt to 'Green' Energy Producers Threatens Investment in New Generation — Expert"
description: "Debts to 'green' electricity producers in Ukraine are nearing 15 billion UAH. Experts warn that this undermines investor confidence and threatens plans to build new generating capacities."
date: 2026-11-20T17:37:23.961Z
lang: en
url: https://xab.info/en/posts/15-billion-uah-debt-to-green-energy-threatens-investment
tags: [ukraine-energy, renewable-energy, green-tariff, ukrenergo, guaranteed-buyer, investment, balancing-market]
author: "Darya Fomina"
publisher: "XAB.info"
---

# 15 Billion UAH Debt to 'Green' Energy Producers Threatens Investment in New Generation — Expert

![Energy infrastructure with smoking thermal power plant chimneys and wind turbines in a field](https://xab.info/media/2026/11/20/dolgi-pered-zelenoy-energetikoy-15-mlrd-grn-ugroza-investitsiyam/dolgi-pered-zelenoy-energetikoy-15-mlrd-grn-ugroza-investitsiyam-1.webp)

## Key Points

- Arrears to renewable energy producers are approaching 15 billion UAH, undermining investor confidence.
- The state plans 5 GW of new generation but has not settled with current investors.
- The NEURC-proposed 2027 transmission tariff (914.02 UAH/MWh) is below Ukrenergo's calculated requirement (964.92 UAH/MWh).
- The 'Guaranteed Buyer' repaid 722.7 million UAH for May and July 2026; July payment level is 75.01%.
- Ukrenergo's debt to Centrenergo for the balancing market is about 1.5 billion UAH.

Accumulated debt to renewable electricity producers in Ukraine is approaching the 15 billion UAH mark, according to experts. Vladimir Omelchenko, Director of Energy Programs at the Razumkov Center, stated that this dynamic undermines investor confidence and calls into question plans to build new generating capacities, including the previously announced 5 GW of maneuverable generation. This is reported by RBC-Ukraine with reference to the expert's statement on Facebook.

### Debt Scale and Payment Chain

According to Omelchenko, investors in renewable energy built power plants, took out loans, and invested their own funds, counting on the state-guaranteed purchase of electricity at the 'green' tariff. However, they are now forced to wait months for payment for already produced electricity. The expert described the mechanism of debt propagation: "Ukrenergo's debts turn into 'Guaranteed Buyer's' debts, and subsequently into arrears to producers." Thus, non-payments at one level of the chain are passed to the next until they reach the end investors.

### Investor Confidence and the 5 GW Plan

The state declares the need to build new maneuverable generation, including the previously announced 5 GW of capacity, but, according to Omelchenko, it has still not ensured full settlement with companies that have already invested in the Ukrainian energy sector. "How does the state intend to convince investors to build new power plants if it cannot fully settle with those who have already invested money in Ukrainian energy?" the expert noted. He emphasized that to attract investment in gas generation, solar and wind power plants, and energy storage systems, financial obligations to existing investors must first be met: "In my opinion, the best signal for future investors is paying off the debts to current ones."

### Transmission Tariff for 2027 as an Additional Risk

As a separate risk factor for debt accumulation, Omelchenko pointed to the NEURC-proposed electricity transmission tariff for 2027 of 914.02 UAH/MWh, which is 1.6% lower than the current level. At the same time, the economically justified need calculated by Ukrenergo is 964.92 UAH/MWh. The gap between the level proposed by the regulator and the grid operator's calculation, according to the expert, creates additional pressure on the sector's financial stability.

### Partial Payments and the Balancing Market Issue

Against the backdrop of total debt, certain payments are still being made but do not cover the full amount. According to the press service of the 'Guaranteed Buyer' JSC, the company fully settled with renewable energy producers for May 2026 by transferring 598.1 million UAH on November 2, and for July, the payment level is 75.01% after a payout of 124.6 million UAH; the total amount of these payments was 722.7 million UAH. In parallel, Serhiy Isachenko, CEO of Centrenergo JSC, previously reported that Ukrenergo's debt to the company for work on the balancing market is about 1.5 billion UAH, forcing the operator to balance between participating in this segment and selling electricity under bilateral contracts with more predictable revenues.

### Demands to the State

Andriy Gerus, Chairman of the Verkhovna Rada Committee on Energy and Housing and Utility Services, previously stated that the state's primary task should be to stop the accumulation of new debts in the balancing market, as directing funds to repay arrears yields no results while non-payments continue to rise. Together, these statements indicate that, according to experts, without a systemic solution to the settlement problem, investor confidence and the implementation of plans to increase generating capacities remain at risk.

## Fact-Check & Sources

- [Долги перед производителями электроэнергии ставят под угрозу инвестиции в новую генерацию, - эксперт](https://www.rbc.ua/ukr/news/borgi-pered-virobnikami-elektroenergiyi-stavlyat-1795195850.html) - Source: Omelchenko's statement on ~15 billion UAH debt, quotes, 914.02/964.92 UAH/MWh tariff, 5 GW plan, 1.5 billion UAH for Centrenergo, Gerus's position.
- [Долги перед производителями электроэнергии в 15 млрд грн ставят под угрозу инвестиции в новую ...](https://www.obozrevatel.com/section-ekonomika-glavnaya/news-borhy-pered-vyrobnykamy-elektroenerhiyi-v-15-mlrd-hrn-stavlyat-pid-zahrozu-investytsiyi-v-novu-heneratsiyu-omelchenko-20-11-2026.html) - Corresponds to the topic and debt amount (15 billion UAH) as of 20.11.2026.
- ["Гарантированный покупатель" погасил долги перед производителями зеленой энергетики на 722,7 млн ...](https://delo.ua/ru/news/garantirovannyi-pokupatel-pogasil-dolgi-pered-proizvoditelyami-zelenoi-energetiki-na-7227-mln-grn-475737/) - Confirms partial payments: May 100% (598.1 million UAH), July 75.01% (124.6 million UAH), total 722.7 million UAH; funds from Ukrenergo.
- [Долги перед "зеленой" энергетикой всё равно придется погасить, – Прокип](https://www.obozrevatel.com/ekonomika-glavnaya/dolgi-pered-zelenoj-energetikoj-vsyo-ravno-pridetsya-pogasit-prokip.htm) - Additional context: delaying obligations increases future costs; aligns with the thesis on the need to pay off debts.

## FAQ

### What is the amount of debt to 'green' electricity producers?

According to Vladimir Omelchenko, Director of Energy Programs at the Razumkov Center, the accumulated debt is approaching 15 billion UAH.

### Why is this important for investors?

The expert points out that the state is declaring the construction of new maneuverable generation (including 5 GW) but has failed to settle with those who already invested, undermining confidence and threatening new projects.

### Are debts being paid partially?

Yes. 'Guaranteed Buyer' JSC settled in full for May 2026 (598.1 million UAH), and for July the payment level is 75.01% (124.6 million UAH); total payments amounted to 722.7 million UAH.

### What is the proposed transmission tariff for 2027?

The NEURC proposed a tariff of 914.02 UAH/MWh, 1.6% lower than the current level; Ukrenergo's calculated requirement is 964.92 UAH/MWh.