# Cold and Hot Testing of the Reactor Begins at Akkuyu NPP Unit 1: A Key Milestone Before Physical Startup

![Panoramic night view of the construction site of the Akkuyu Nuclear Power Plant in Turkey with illuminated structures](https://xab.info/media/2026/11/18/akkuyu-aes-holodno-goryachaya-obkatka-reaktora/akkuyu-aes-holodno-goryachaya-obkatka-reaktora-1.webp)

## Key Points

- On November 15, 2026, NDK issued a permit for cold and hot testing of Unit 1 reactor at Akkuyu NPP
- The coolant will be heated to 285 °C at 16.5 MPa; fuel simulators are placed in the core
- On October 27, secondary circuit hydraulic tests at 12.6 MPa were successfully completed
- Loading real fuel will require a separate permit from the Turkish regulator

The penultimate stage of commissioning has started at Unit 1 of Turkey’s Akkuyu Nuclear Power Plant — the cold and hot testing of the reactor facility. The Nuclear Regulatory Agency of Turkey (NDK) issued the permit to conduct the tests on November 15, 2026. This means the plant, being constructed by Rosatom under the Build-Own-Operate model, is nearing the stage of nuclear fuel loading and the physical startup of the reactor.

### What is Cold and Hot Testing

During this stage, specialists test the equipment of the primary and secondary circuits under conditions as close to operational as possible. The reactor facility is gradually heated: the coolant temperature is brought to 285 °C and the pressure to 16.5 MPa. It is under these parameters that the strength of the equipment and pipelines is assessed, vibration characteristics are checked, as well as the power supply, control, and safety systems. Crucially, fuel assembly simulators are placed in the reactor core instead of nuclear fuel at this stage — real fuel assemblies will only appear during the physical startup phase.

### Preceding Tests: Secondary Circuit Strength

Before the cold and hot testing began, hydraulic strength tests of the secondary circuit at Unit 1 had already been completed, as reported by Rosatom on October 27, 2026. For three days, specialists checked the steam generators, steam valve blocks, and feedwater pipelines. All four steam generators and their connected pipelines were tested at a pressure of 12.6 MPa — 15% above the design operating pressure. By comparison, a comparable pressure in the natural environment is created in the ocean at a depth of about 1.25 kilometers. Before increasing the pressure, the steam generators were heated to 126 °C, and the maximum water temperature during the tests reached 135 °C. The pressure was raised in stages, with equipment parameters and joint tightness monitored at each level. The tests confirmed the equipment's resistance to increased pressure, as well as the quality of installation and welded joints.

### What Follows the Testing

Upon completion of the cold and hot testing, specialists will conduct an inspection of the equipment to confirm its compliance with design requirements and its readiness for physical startup. Loading actual nuclear fuel into the reactor core will require a separate permit from the Turkish regulator, NDK. Thus, between the current stage and the first physical startup, there remains another administrative and technical cycle, but the primary engineering tests of the reactor facility will essentially be completed at this stage.

### Context: The Akkuyu NPP Project

Akkuyu NPP is the first nuclear power plant in Turkey's history. The project is being implemented by the Russian state corporation Rosatom and includes four power units with Generation 3+ VVER reactors of 1,200 MW each. The plant is being built under the Build-Own-Operate model, which involves investor participation at all stages — from construction to long-term operation. The launch of the first unit will be a milestone for Turkey’s energy sector, which has relied predominantly on gas and hydroelectric power plants for decades.

## Fact-Check & Sources

- [Реактор разогреют до 285 °C: на первом энергоблоке АЭС «Аккую» начались ключевые испытания](https://www.ixbt.com/news/2026/11/18/reaktor-razogreiut-do-285-c-na-pervom-energobloke-aes-akkuiu-nacalis-kliucevye-ispytaniia.html) - Primary source. Confirms permit date (15.11.2026), testing parameters (285 °C, 16.5 MPa), presence of fuel simulators, BOO model, unit capacity of 1,200 MW, VVER 3+ reactor type.
- [На первом энергоблоке АЭС «Аккую» (Турция) подтверждена прочность оборудования второго контура](https://www.ruscable.ru/news/2026/10/27/_Na_pervom_energobloke_AES_Akkuu_Turtsiya_podtve/) - Contextual source. Confirms completion of secondary circuit hydraulic tests on 27.10.2026, pressure of 12.6 MPa, temperature of 126–135 °C, three days of testing, four steam generators.

## FAQ

### What is cold and hot reactor testing?

It is a commissioning stage where the reactor facility is heated to operating parameters (285 °C and 16.5 MPa at Akkuyu) without nuclear fuel to test equipment strength, vibrations, control, and safety systems under near-operational conditions.

### When is the physical startup of Akkuyu NPP Unit 1 planned?

The exact date of physical startup is not specified in the provided sources. Following the completion of testing and equipment inspection, a separate NDK permit for fuel loading will be required, which determines the timeline.

### What type of reactors are installed at Akkuyu NPP?

Four power units with Generation 3+ VVER reactors of 1,200 MW each. The project is implemented by Rosatom under the Build-Own-Operate model.

### What tests were conducted prior to the cold and hot testing?

On October 27, 2026, secondary circuit strength hydraulic tests were completed: steam generators and pipelines were tested at 12.6 MPa (15% above working pressure) at temperatures up to 135 °C for three days.