# Heat Pipeline on Teremky: Kyiv City Council Warns of Risk of Leaving 200,000 Residents Without Backup Heating Due to Missed Deadlines

![Workers laying heating pipeline pipes in Kyiv's Teremky district — installation of backup heat supply line](https://xab.info/media/2026/09/22/teplotrassa-teremki-kgga-risk-otopleniya/teplotrassa-teremki-kgga-risk-otopleniya-1.webp)

## 🎯 Key Points

- Construction of the heat pipeline in Teremky was halted for 1.5 months to coordinate the project with activists; the number of trees to be removed was reduced from 200 to 5–10
- The KCCA warns of critically compressed deadlines: without completing the work before the heating season, more than 200,000 residents of the Holosiivskyi district risk being left without backup heat
- The project has passed state expertise, is an element of the energy resilience plan, and is not linked to commercial construction
- There are discrepancies between the KCCA's statements about the absence of felling and media reports of an alleged resumption of felling on September 21, 2026

In Kyiv, amid ongoing public debate over the construction of a backup heat pipeline in the Teremky-1 and Teremky-2 residential districts, acting First Deputy Head of the Kyiv City Council (KCCA) Pyotr Panteleev stated that work on laying the mainline had been forced to halt for a month and a half in order to coordinate the project with local activists. During this period, around ten open-format meetings were held, at which scientists and experts were brought in to seek alternative solutions. According to Panteleev, the community's initial request to preserve the trees was fulfilled: if the original project version provided for the removal of up to 200 green plantings, the optimized version now involves only five to ten trees. At the same time, the KCCA claims that since work resumed, not a single green planting has been damaged.

### Critically Compressed Deadlines and Threat to Winter Heating

The main problem highlighted by the KCCA is the extremely tight deadline for completing construction. Panteleev emphasized that almost two months have already been lost, and the state enterprise 'Kyivteploenergo' is obliged to continue work in order to finish laying the pipeline before the start of the heating season. In the previous heating cycle, serious problems with heat supply were recorded in Teremky: after massive shelling, residents of the district were left without heat for a prolonged period. The backup heat pipeline currently being laid is designed to ensure stable heat supply to nearly 200 residential buildings and other structures in the event of damage to the TEC-5 power plant. According to KCCA data, the project covers more than 200,000 residents of the Holosiivskyi district.

### Project Is Not Linked to Commercial Construction

The KCCA separately stressed that the project being implemented has passed state expertise and is one of the elements of the city's energy resilience plan. Panteleev stated that the heat pipeline is not connected to any commercial project or housing construction. At the construction site, law enforcement agencies and the municipal enterprise 'Municipal Guard' are currently working, ensuring public order and enhanced security requirements. The KCCA declared its readiness to 'argue the project in detail' and expects a constructive approach from the residents' activist group.

### Contradictory Data

There are discrepancies between the KCCA's statements and reports from a number of media outlets at the scene. On the one hand, Pyotr Panteleev claims that since work resumed, not a single green planting has been damaged and that no tree felling is being carried out. On the other hand, on September 21, 2026, reports of an alleged resumption of tree felling for the laying of the heat network were recorded in the Teremky area. In addition, the initial version of the KCCA's statement mentions a range of '5–10 trees,' whereas in a number of publications citing the same KCCA representatives, the specific figure of '10 trees' is given. These inconsistencies require additional factual verification on the ground.

### Context: Why the Dispute Is Not Subsiding

The conflict over the heat pipeline in Teremky has become one of the most resonant examples of a clash between environmental activism and infrastructure necessity in wartime conditions. The residents of the district, who in the previous heating season experienced multi-day heat outages after strikes on energy facilities, in theory should be the main beneficiaries of the backup mainline. Yet it is precisely they who are initiating the preservation of the green fund, which, in their view, is an integral part of the quality of life in a residential district. The KCCA insists that the optimized project already takes these requirements into account, and that any further blocking of the work creates a real risk to winter heat supply for tens of thousands of people.

## 🔍 Fact-Check Verification

- [Work was halted for 1.5 months: KCCA warns of risks to heating in Teremky due to protests](https://www.rbc.ua/ukr/news/roboti-zupinyali-1-5-misyatsi-kmda-zayavili-1790092462.html) - Основной источник брифинга Пантелеева. Подтверждает 1,5-месячную остановку, 10 встреч, сокращение вырубки с 200 до 5-10 деревьев, риски для зимнего отопления.
- [A backup heat pipeline is being laid in Teremky, but no new tree felling is being carried out – KCCA](https://ru.interfax.com.ua/news/general/1207444.html) - Подтверждает факт прокладки теплотрассы и отсутствие новой вырубки по данным КГГА.
- [Tree felling for the laying of a heat network allegedly resumed in the Teremky area of Kyiv: what ...](https://24tv.ua/ru/vyrubka-derevev-na-teremkah-v-kieve-chto-proizoshlo-21-sentjabrja-2026-goda_n3146045) - Содержит сообщения о якобы возобновившейся вырубке 21.09.2026, что противоречит заявлениям КГГА. Использовано в блоке 'Противоречивые данные'.
- [Changes to be made to the heat network project in Teremky, only 10 trees to be removed – KCCA](https://ukranews.com/news/1174370-v-proekt-teploseti-na-teremkah-vnesut-izmeneniya-udalyat-vsego-10-derevev-kgga) - Подтверждает внесение изменений в проект. Указывает конкретную цифру 10 деревьев, тогда как в брифинге РБК — диапазон 5-10.

## ❓ FAQ

### Q: How many trees will be removed during the construction of the heat pipeline in Teremky?
**A:** According to the KCCA, the optimized project provides for the removal of 5–10 trees instead of the initial 200. In a number of publications citing the same KCCA representatives, the specific figure of 10 trees is mentioned.

### Q: Why is the backup heat pipeline being built in Teremky?
**A:** The heat pipeline provides backup heat supply to nearly 200 residential buildings and more than 200,000 residents of the Holosiivskyi district in the event of damage to the TEC-5 power plant. The project is an element of the energy resilience plan and has passed state expertise.

### Q: Why was the work stopped and how much time has been lost?
**A:** Work was stopped for a month and a half to hold around ten meetings with activists and to coordinate the optimized project that preserves green plantings. The KCCA notes that almost two months have already been lost, and the completion deadlines are critically compressed.

### Q: Is the heat pipeline linked to any commercial construction project?
**A:** No. The KCCA explicitly stated that the project is not connected to any commercial project or construction. It is being implemented by the state enterprise 'Kyivteploenergo' as a measure of the city's energy resilience.