title: "Hungary begins sinking barges in the Danube to save the Paks NPP from shutdown"
description: "🇭🇺 Hungary has launched an emergency operation to save the Paks NPP from shutdown due to drought. Authorities have sunk barges in the Danube and are building an underwater barrier to raise the water level. The plant is operating at only 25% capacity. A complete shutdown would cost the economy $159 million per month. Prime Minister Magyar has cast doubt on the Paks II project with Russia. 🇪🇺 The crisis has engulfed all of Europe: Romania and France have also shut down reactors."
date: 2026-08-15T19:16:57.000Z
lang: en
url: https://xab.info/en/posts/hungary-sinks-barges-in-danube-to-save-paks-npp
tags: [hungary, nuclear-energy, paksh-2, drought, economy, climate-crisis]
publisher: "XAB.info"
---

# Hungary begins sinking barges in the Danube to save the Paks NPP from shutdown

![Barges on the Danube River in Hungary, used for flooding to support the Paks Nuclear Power Plant](https://xab.info/media/2026/08/15/vengriya-zatopila-barzhi-v-dunae-dlya-spaseniya-ae/vengriya-zatopila-barzhi-v-dunae-dlya-spaseniya-ae-1.webp)

## 🎯 Key Points

- The Paks NPP is operating at 25% capacity due to the shallowing of the Danube.
- Hungary has sunk barges and is building an underwater barrier to raise the water level.
- A complete shutdown of the plant will cost the economy $159 million per month.
- Prime Minister Magyar has cast doubt on the Paks II project with Russia.
- The crisis has engulfed all of Europe: Romania and France have also shut down reactors.

Hungary has resorted to unprecedented engineering measures to prevent an energy collapse. Due to a critical drop in the water level of the Danube River, caused by extreme drought, the country's authorities have launched an operation to artificially raise the water level near the Paks Nuclear Power Plant. This is necessary to keep the country's only nuclear power plant running, which is currently operating at only a quarter of its capacity.

### Critical water levels and the threat of shutdown

As of August 15, 2026, the water level in the Danube at the water intake collectors of the Paks NPP has dropped to the minus 122 cm mark. Hydrologists warn that without intervention, the situation will worsen: by Sunday, a drop to minus 132 cm is expected, which will require the emergency shutdown of another turbine. The critical point is the minus 140 cm mark; upon reaching it, the plant will be forced to stop operations completely due to the inability to draw water for reactor cooling.

### Engineering operation: sinking barges and an underwater barrier

To buy time, the Hungarian government has deployed the army and special equipment. In the closed waters of the plant, two 80-meter barges were positioned perpendicular to the current and secured with 5-ton anchors. Industrial divers are conducting an operation to sink them in a controlled manner to create a temporary dam. This should raise the water level in front of the intake by at least 20 cm. Simultaneously, 100 soldiers are working around the clock to build an underwater stone sill on the riverbed, which requires the delivery of 150,000 cubic meters of stone.

### Financial risks and political context

A complete shutdown of the Paks NPP would inflict colossal damage on the country's economy. According to calculations, the emergency purchase of imported electricity will cost the treasury at least $159 million per month. Authorities fear that further shallowing of the river will lead to the plant's shutdown, which will cost the economy at least $159 million monthly. Against this backdrop, Prime Minister Péter Magyar launched a harsh political attack on the opposition, accusing the previous authorities of strategic negligence and unpreparedness for climate challenges.

### Contradictory data

There are discrepancies in the assessments of the prospects for the Paks II project. On the one hand, Prime Minister Péter Magyar officially expressed doubts about the expediency of completing the construction of new Russian reactors, stating that building new energy blocks while the Danube dries up is economic suicide. On the other hand, sources indicate that the project remains strategically important for the country's energy security, and the question of its implementation will be reviewed, but not cancelled outright. The opposition, however, insists on a complete halt to cooperation with Rosatom until the cooling problems are resolved.

### European context

The problem is not limited to Hungary. Neighboring Romania has already completely shut down its Cernavodă NPP due to similar shallowing of the Danube. In France, due to river overheating and anomalous heat, the Ministry of Energy was forced to forcibly shut down 6 out of 57 nuclear reactors. The situation in Hungary has become part of a large-scale European energy crisis caused by climate change and extreme weather conditions.

## 🔍 Fact-Check Verification

- [Magyar found a pretext to bargain with Russia over the Paks II NPP](https://vz.ru/politics/2026/7/18/1435698.html) - Подтверждает политический контекст и сомнения в проекте «Пакш-2».
- [Prime Minister Magyar: Hungary intends to review the agreement with Russia on the Paks II NPP](https://1prime.ru/20260731/vengrija-871945699.html) - Подтверждает намерение пересмотреть соглашение с РФ.
- [EU convenes emergency session due to the shutdown of the Paks NPP in Hungary](https://ru.euronews.com/my-europe/2026/07/31/eu-meeting-hungary-nuclear-plant-stopped) - Подтверждает европейский контекст и экстренное заседание ЕС.
- [Paks NPP may be completely shut down due to the shallowing of the Danube](https://neftegaz.ru/news/nuclear/931527-aes-paksh-mogut-polnostyu-ostanovit-iz-za-obmeleniya-dunaya/) - Подтверждает угрозу полной остановки АЭС из-за обмеления Дуная.

## ❓ FAQ

### Q: Why did Hungary start sinking barges in the Danube?
**A:** To artificially raise the water level near the Paks NPP to prevent the shutdown of the plant due to critical shallowing of the river.

### Q: What is the current capacity of the Paks NPP?
**A:** The plant is operating at 25% of its capacity, which amounts to 485 MW out of the base 2,000 MW.

### Q: How much will a complete shutdown of the NPP cost?
**A:** The emergency purchase of imported electricity will cost the treasury at least $159 million per month.

### Q: What does Prime Minister Magyar say about the Paks II project?
**A:** He expressed doubts about the expediency of completing the construction of new Russian reactors due to cooling problems in drought conditions.

### Q: Are there similar problems in other European countries?
**A:** Yes, Romania has shut down the Cernavodă NPP, and France was forced to disconnect 6 reactors due to river overheating.