# Part of Kyiv's Livoberezhnyi district to face temporary heating cuts due to valve installation

![A woman sits by the window and warms her hands on a radiator in an apartment in the evening](https://xab.info/media/2026/11/17/kiev-levoberezhie-vremenno-bez-tepla/kiev-levoberezhie-vremenno-bez-tepla-1.webp)

## Key Points

- From November 18, the installation of shut-off valves will begin in Kyiv's Livoberezhnyi district, requiring a shutdown of a heating main section.
- Some residential and institutional buildings will be temporarily without heat; the work is being managed by the State Agency for Infrastructure Restoration.
- The shutdown coincides with the repair of the Northern and Southern bridge heating mains, which were damaged on the night of November 17.

On the left bank of Kyiv, some residential, institutional, and other buildings will be temporarily left without heat supply. This was reported by the Kyiv City State Administration (KCSA) in connection with the ongoing construction of backup heating systems in the city's Livoberezhnyi district.

### What is happening in the Livoberezhnyi district

According to the KCSA, construction of backup heating systems is underway on the left bank of the capital, and the assembly work requires a temporary shutdown of a section of the heating main. The State Agency for Restoration and Development of Infrastructure of Ukraine is the client for the works. Starting Wednesday, November 18, construction crews will begin installing shut-off valves, which requires disconnecting the relevant section of the heating main.

### Why the heating main is being shut down

As the administration explained, during the assembly work, some residential, institutional, and other buildings in the Livoberezhnyi district will temporarily remain without heat supply. The KCSA emphasized that the work is planned to be completed in the shortest possible time to restore heat delivery as quickly as possible. The organization of the work has been submitted to the municipal commission for techno-ecological safety and emergencies to ensure coordination and interaction between all responsible parties.

### Link to the consequences of infrastructure attacks

The heating shutdown on the left bank is occurring against the backdrop of damage sustained by Kyiv's energy infrastructure. On the night of November 17, as a result of a Russian attack, the heating mains of the Northern and Southern bridges of the capital were damaged. Some consumers were transferred to backup heating in connection with this, and hot water supply was temporarily disconnected. Thus, the construction work on the Livoberezhnyi heating main coincides with the period of restoring the city's damaged heat supply sections.

### Organization of work and timeline

The KCSA assured that the installation work for the shut-off valves will be carried out in a tight timeframe to ensure the fastest possible restoration of heat to the affected buildings. Coordination of contractor actions and public utilities will be handled by the municipal commission for techno-ecological safety and emergencies. Residents of the Livoberezhnyi district have been informed about the temporary nature of the shutdown during the construction of backup heating systems.

## Fact-Check & Sources

- [Часть зданий Левобережного массива Киева временно останется без тепла, - КГГА](https://www.rbc.ua/ukr/news/chastina-budivel-livoberezhnogo-masivu-kieva-1794940984.html) - Primary source: KCSA statement on valve installation starting Nov 18, client is the Infrastructure Restoration Agency, temporary heat cuts on the left bank.
- [На левом берегу Киева временно отключат теплоснабжение — что известно](https://unn.ua/ru/news/na-levom-beregu-kieva-vremenno-otklyuchat-teplosnabzhenie-chto-izvestno) - Confirms dates and reason; adds that the matter was referred to the municipal commission for safety and emergencies.
- [На левом берегу Киева с 18 ноября часть домов временно останется без отопления — КГГА](https://sud.ua/ru/news/ukraine/377920-na-livomu-berezi-kyieva-z-18-lystopada-chastyna-budynkiv-tymchasovo-zalyshytsia-bez-opalennia-kmda) - Confirms temporary heating shutdown for parts of the Livoberezhnyi district from Nov 18 due to heating main maintenance.

## FAQ

### When will the heating shutdown in Kyiv's left bank start?

Starting Wednesday, November 18, 2026, construction crews will begin installing valves, which requires shutting down a heating main section.

### Who is carrying out the work and why is it needed?

The client is the State Agency for Restoration and Development of Infrastructure of Ukraine. The work is part of the construction of backup heating systems.

### How long will the shutdown last?

The KCSA reported that the work is planned to be completed as soon as possible to restore heat supply to the affected buildings quickly.