title: "Minpromtorg Files Two Lawsuits Totaling 338.7M Rubles Against Milandr Over Delayed Gigabit Ethernet R&D"
description: "Minpromtorg has filed two lawsuits totaling 338.7 million rubles against Milandr in the Moscow Arbitration Court for delayed Gigabit Ethernet chip R&D, completed nearly nine years late. The company considers the demands groundless."
date: 2026-11-26T00:23:20.042Z
lang: en
url: https://xab.info/en/posts/milandr-minpromtorg-lawsuits-338-million-rubles
tags: [milandr, minpromtorg, microelectronics, gigabit-ethernet, russia]
author: "Roman V."
publisher: "XAB.info"
---

# Minpromtorg Files Two Lawsuits Totaling 338.7M Rubles Against Milandr Over Delayed Gigabit Ethernet R&D

![Electronic printed circuit board with a microchip and processor chip inside a server rack](https://xab.info/media/2026/11/26/milandr-minpromtorg-isk-338-mln-rubley/milandr-minpromtorg-isk-338-mln-rubley-1.webp)

## Key Points

- Minpromtorg filed two lawsuits against Milandr totaling 338.7 million rubles (290 million and 48.7 million), registered on November 23, 2026.
- Gigabit Ethernet R&D, started in 2015, was actually completed in September 2026—almost nine years late.
- In 2019, the court already rejected the agency's penalty claim, recognizing no fault on the developer's part; the company expects a similar outcome.
- R&D delays are a systemic issue: in 2026, penalties were also issued to OKB Planeta, SKTB ES, and NIAI Istochnik.

Russia's Ministry of Industry and Trade (Minpromtorg) has filed two new lawsuits against microelectronics developer JSC PCC Milandr with the Arbitration Court of Moscow, totaling 338.7 million rubles. According to the agency, the company violated the deadlines for performing work under a state contract. The lawsuits were registered on November 23, 2026: under the first claim, the ministry is demanding the recovery of 290 million rubles, and under the second, 48.7 million. The company itself calls the claims groundless and has stated its intention to defend its position in court, citing a precedent where the court previously ruled that the developer bore no fault for the delay.

### Nine Years for One Chipset

The disputed state contract worth 300 million rubles was concluded in 2015 as part of research and development (R&D) work to create a Gigabit Ethernet interface chipset. Milandr was supposed to develop a 16-port switch—a functional analog of solutions by the American company Marvell—while the project partner, STC Module, was responsible for the physical layer PHY microchips. Initially, the work was planned to be completed by the end of 2017, but the project was actually finished only in September 2026, nearly nine years behind schedule.

### First Recovery Attempt: Court Sides with the Developer

By November 2019, the work had still not been delivered, and the ministry levied a penalty of 37.6 million rubles, filing a lawsuit. In December of the same year, the Arbitration Court of Moscow completely dismissed the claims, taking into account the specifics of R&D work, excessively high technical requirements, restrictions on the use of foreign components, and delays on the part of the partner. Milandr considers this outcome to be a key argument in favor of its position in the new proceedings.

### A Systemic Industry Problem

The claims against Milandr are not an isolated case. In early 2026, Minpromtorg actively issued penalties to Russian microelectronics developers for missing R&D deadlines: OKB Planeta received three notifications of fines totaling 80 million rubles, JSC SKTB ES faced a 274 million ruble penalty for a six-year delay in chip development, and NIAI Istochnik was fined 181 million rubles. Manufacturers, in turn, explain the delays by the complexity of developments, sanctions restrictions, and component supply problems, while courts frequently side with contractors if they prove that the delay was not their fault.

### Positions of the Parties

Milandr insists that in the previous legal proceedings it successfully proved its lack of fault in the delay and is counting on a similar decision in the new lawsuits. Minpromtorg declined to comment on the filed claims. Thus, the outcome of the case will once again depend on whether the developer can convince the court that the deadline disruption was caused by external factors and the specifics of R&D rather than the contractor's actions.

## Accounts differ

### Justification of penalty recovery for deadline disruption

- **Minpromtorg:** Claims that Milandr violated the deadlines for performing work under the state contract and demands the recovery of penalties totaling 338.7 million rubles. ([ixbt.com](https://www.ixbt.com/news/2026/11/25/rossiiskaia-kompaniia-deviat-let-sozdavala-mikrosxemy-gigabit-ethernet-na-zamenu-amerikanskim-cipam-marvell-teper-minpromtorg-trebuet-339-mln.html))
- **JSC PCC Milandr:** Considers the demands groundless and cites that in the previous proceedings, the company successfully proved its lack of fault in the delay. ([ixbt.com](https://www.ixbt.com/news/2026/11/25/rossiiskaia-kompaniia-deviat-let-sozdavala-mikrosxemy-gigabit-ethernet-na-zamenu-amerikanskim-cipam-marvell-teper-minpromtorg-trebuet-339-mln.html))

*Where they agree:* Both parties acknowledge that work under the 2015 contract was completed later than the initial deadline (actually in September 2026).

## Fact-Check & Sources

- [Российская компания девять лет создавала микросхемы Gigabit Ethernet на замену американским чипам Marvell — теперь Минпромторг требует 339 млн](https://www.ixbt.com/news/2026/11/25/rossiiskaia-kompaniia-deviat-let-sozdavala-mikrosxemy-gigabit-ethernet-na-zamenu-amerikanskim-cipam-marvell-teper-minpromtorg-trebuet-339-mln.html) - Confirmed lawsuit amounts (290 million and 48.7 million), registration date November 23, 2026, 2015 contract parameters, 2019 court outcome, and context regarding other developers.

## FAQ

### What is the total amount of Minpromtorg's lawsuits against Milandr?

The total amount of the two lawsuits is 338.7 million rubles: 290 million and 48.7 million rubles. The lawsuits were registered in the Arbitration Court of Moscow on November 23, 2026.

### Why is Minpromtorg filing claims?

The agency points to a violation of deadlines for work under a 2015 state contract to develop a Gigabit Ethernet interface chipset, which was actually completed only in September 2026.

### How is Milandr reacting to the lawsuits?

The company considers the demands groundless and intends to defend its position, citing that in 2019 it successfully proved its lack of fault in the delay.