title: "Nearly UAH 4 Billion in Disputed RES Imbalance Charges Remain Unsettled Despite Court Ruling"
description: "Nearly UAH 4 billion in disputed green electricity imbalance charges remain unsettled despite a court ruling invalidating the NEURC formula, an ICC expert stated."
date: 2026-11-29T16:07:40.176Z
lang: en
url: https://xab.info/en/posts/nearly-4-billion-uah-disputed-res-imbalance-charges
tags: [renewable-energy, ukraine, energy-market, ncrku, imbalance-charges, investments]
author: "Darya Fomina"
publisher: "XAB.info"
---

# Nearly UAH 4 Billion in Disputed RES Imbalance Charges Remain Unsettled Despite Court Ruling

## Key Points

- Nearly UAH 4 billion in disputed RES imbalance charges remain unsettled despite a court ruling invalidating the NEURC formula.
- In 2022, green electricity producers bore responsibility for the Guaranteed Buyer's trading decisions as well, with charges exceeding 50% of revenue in rare cases.
- Experts propose legally defining a mechanism to review the consequences of applying the invalidated formula and to settle mutual obligations.
- Total debts to RES producers, according to the Razumkov Centre, are approaching UAH 15 billion.

Nearly UAH 4 billion in disputed electricity imbalance charges from renewable sources still remain unsettled, despite a court ruling invalidating the respective NEURC calculation formula. This was stated by ICC Vice President for Energy Olexandr Trokhymets while assessing the state of financial settlement in the green energy sector.

### Responsibility for Others' Trading Decisions

According to the expert, unresolved financial issues from past years create systemic problems for RES producers and require legislative settlement. In 2022, a difficult period for Ukraine's energy sector, green electricity producers, in his estimation, bore financial responsibility not only for their own imbalances, but also for the trading decisions of the Guaranteed Buyer, which they had no ability to influence. In rare cases, as Trokhymets noted, the respective charges exceeded 50% of the enterprises' revenue.

### Court Ruling and Its Practical Consequences

The expert recalled that the court declared the imbalance calculation formula invalid. According to his interpretation, such a decision should serve as the basis for recalculating funds for the entire period the formula was applied, since invalidation means the formula did not exist retroactively—throughout its entire effective term. However, as Trokhymets emphasized, NEURC has still not resolved this issue, and the charges for February–September 2022 remain a subject of dispute.

### Impact on the Investment Climate

Despite the development of Ukraine's renewable energy sector and efforts to attract international investors, unresolved financial obligations from past years continue to be a problem for the industry. To solve this, experts propose legally defining a mechanism to review the consequences of applying the formula recognized invalid by the court and to settle mutual obligations among market participants. Trokhymets expressed confidence that such a decision would be an important step in strengthening investor confidence in Ukraine's energy sector.

### Fair Rules for Operating Companies

The expert emphasized that attracting new investments must be accompanied by ensuring fair and predictable rules for companies already operating in the country. According to him, it is necessary not only to create conditions for new investments, but also to demonstrate the ability to provide stable rules for those already working in Ukraine.

### Context: The General Picture of Debts in Energy

Earlier, Volodymyr Omelchenko, Director of Energy Programs at the Razumkov Centre, stated that debts to electricity producers from renewable sources are approaching UAH 15 billion. According to him, investors who built power plants, attracted loans, and invested their own funds are forced to wait months for payment for electricity already generated. Ivan Plachkov, President of the Ukrainian Energy Assembly and former Minister of Fuel and Energy, in turn, noted that debts in the energy sector had accumulated over years and were ignored at a critical moment of market reform.

## Fact-Check & Sources

- [Почти 4 млрд грн спорных начислений перед производителями ВИЭ остаются неурегулированными, - эксперт](https://www.rbc.ua/ukr/news/mayzhe-4-mlrd-grn-spirnih-narahuvan-pered-1795965027.html) - Primary source: statement by ICC Vice President for Energy Olexandr Trokhymets regarding UAH 4 billion in unsettled charges and the court ruling on the formula's invalidity.
- [Почти 4 млрд грн спорных начислений перед производителями ВИЭ остаются неурегулированными ...](https://www.obozrevatel.com/section-ekonomika-glavnaya/news-mayzhe-4-mlrd-hrn-spirnykh-narakhuvan-pered-vyrobnykamy-vde-zalyshayutsya-nevrehulovanymy-trokhymets-29-11-2026.html) - Reprint of RBC-Ukraine material, facts and quotes match the primary source.

## FAQ

### What is the amount of disputed RES imbalance charges?

According to ICC Vice President for Energy Olexandr Trokhymets, nearly UAH 4 billion in disputed green electricity imbalance charges remain unsettled.

### Why do the charges remain disputed?

The court declared the imbalance calculation formula invalid, which, according to the expert's interpretation, should be the basis for recalculating funds for the entire period of its application, yet NEURC has still not resolved this issue.

### What period do the disputed charges cover?

The charges for February–September 2022 remain disputed.

### What solution do experts propose?

Experts propose legally defining a mechanism at the legislative level to review the consequences of applying the court-invalidated formula and to settle mutual obligations of market participants.