# Vinohradar Metro Tunnel Ready: Traffic on European Union Avenue Expected to Return by Christmas

![Road construction machinery working on a sandy site in the center of a residential district in Kyiv](https://xab.info/media/2026/11/24/tonnel-metro-vinogradar-gotov-dvizhenie-po-prospektu-evropeiskogo-soyuz/tonnel-metro-vinogradar-gotov-dvizhenie-po-prospektu-evropeiskogo-soyuz-1.webp)

## Key Points

- The metro tunnel under European Union Avenue is finished; utility work and road restoration are underway.
- Contractor Autostrada reports about 80% completion of the works.
- 460 out of 750 meters of the storm drain collector have been installed via microtunneling.
- Over 70% of Herrenknecht equipment for the 'Victoria' TBM delivered; next step is the left tunnel excavation.
- Traffic on European Union Avenue is planned to resume by Christmas.

In Kyiv, the excavation of the Vinohradar metro tunnel under European Union Avenue has been completed — a key stage in the construction of the new section of the Syretsko-Pecherska line. As reported by RBC-Ukraine with reference to the contractor Autostrada, work is now concentrated on this section on utility systems installation and road surface restoration. The contractor claims that about 80% of the planned work has been completed, and traffic is scheduled to resume by Christmas.

### Utility Systems: Relocation and Road Restoration

Storm and sewage systems are being built on the site, drainage systems are being set up, and utility lines—water, heating, gas, high-voltage cables, and telecommunications—are being relocated. In areas where relocation is complete, road crews have begun restoring the carriageway and sidewalks. Specifically, on European Union Avenue from the direction of Svobody Avenue, old asphalt concrete is being milled, and the structural layers of the road base are being replaced.

### Microtunneling and the "Victoria" Shield

In parallel, a new storm drain collector is being built using the microtunneling method: according to the contractor, 460 meters out of 750 have already been laid. The main components and systems for the "Victoria" tunnel boring machine are being assembled on-site, with over 70% of the new equipment from the German company Herrenknecht already delivered. After assembly and commissioning, the complex will begin the excavation of the left tunnel between the "Syrets" and "Mostytska" stations.

### When Traffic Will Reopen

Autostrada emphasizes that work on the site is being carried out around the clock. The company intends to finish major construction work on European Union Avenue as soon as possible and resume traffic by Christmas. The contractor notes that approximately 80% of the planned work on this section is done.

### Context: Closures Since April 2026

Previously, RBC-Ukraine reported that in April 2026, the partial closure of European Union Avenue was extended due to the construction of the Vinohradar metro. Restrictions on the section from Vasyl Poryk Avenue to Svobody Avenue, which were initially set to last until April 5, 2026, were extended until December. Construction on the new section of the Syretsko-Pecherska metro line continues in this area: ground transport is operating on temporary routes, and drivers are advised to bypass the closed section via Poryk and Svobody Avenues.

## Fact-Check & Sources

- [Тоннель метро на Виноградарь готов: когда возобновят движение по проспекту Европейского Союза](https://www.rbc.ua/ukr/news/tunel-metro-vinogradar-gotoviy-koli-vidnovlyat-1795518028.html) - Primary source; Autostrada data: ~80% work, 460/750m microtunneling, >70% Herrenknecht gear for 'Victoria', traffic restart by Christmas, context of closures since April 2026.

## FAQ

### What has been finished on European Union Avenue?

The Vinohradar metro tunnel excavation is complete; crews are currently installing utility networks and restoring the road.

### When will traffic return?

According to the contractor, Autostrada, traffic is expected to return by Christmas, with work proceeding 24/7.

### How much of the storm drain collector has been installed?

460 meters out of the planned 750 have been laid using microtunneling.