The parameters of the large-scale project by Amazon Web Services (AWS) and the Greek state-owned Public Power Corporation (PPC) were revealed in a 737-page environmental impact assessment. The data center will be built on the site of the former Agios Dimitrios coal-fired power plant in Kozani, northern Greece. The complex will occupy about 45 hectares, with a total floor area of 77,360 m² across four buildings. Each building will house five server halls with a computing capacity of 12 MW each, totaling 240 MW of IT equipment. Factoring in cooling and auxiliary systems, electricity consumption will reach up to 300 MW.

Power Infrastructure Reconstruction

A key feature of the project is the reuse of the coal plant's preserved electrical infrastructure, which previously handled up to 1.55 GW of power transmission. The data center will connect to the existing 400 kV substation via two new underground cable lines. Under the agreement, AWS will purchase electricity from PPC through long-term renewable energy supply contracts. The division of roles is clear: PPC provides the site, buildings, and energy infrastructure, while Amazon installs and operates the computing equipment.

Cooling and Heat Recovery

The assessment outlines a hybrid cooling system: water cooling will account for 60–90% of the load, with air cooling handling the rest. Water consumption at full capacity is estimated at approximately 203,000 m³ per year, which will be sourced from the Polyfytos reservoir using the power plant's existing infrastructure. The document also includes the potential to use server heat to warm residential homes, schools, and medical facilities, with an estimated heat recovery potential of about 822,600 MWh of thermal energy per year.

Investment and Timeline

Investment in the first phase of the project is estimated at roughly €2 billion: PPC will allocate about €1 billion for buildings and energy infrastructure, and Amazon will invest a comparable amount in IT equipment. Meanwhile, PPC's own strategic plan previously estimated capital expenditures for the first phase at €1.2 billion. The 300 MW grid connection agreement is expected to be finalized in the first quarter of 2027, with construction slated to begin in the summer of 2027 and finish by the end of 2028.

Potential Expansion to 1 GW

Amazon also holds an exclusive right until the end of May 2027 to expand the project up to 1 GW. If the company exercises this option, the second phase could begin development in the autumn of 2027, with grid connection scheduled for 2031. Thus, the project transforms from a local IT infrastructure initiative into one of Europe's largest data center clusters, built on decommissioned coal-fired generation assets.