Construction of Oracle data center in the desert: delayed Green Chile pipeline threatens Project Jupiter

Project Jupiter Crisis: Green Chile Pipeline Delayed to 2027, Threatening Oracle Data Center

Technology 08/17/2026, 04:54
🚧 Critical delay for Oracle Data Center: Green Chile pipeline postponed to 2027. 🔹 Project Jupiter (OpenAI + Oracle) worth $165 billion faces a schedule breach. 🔹 Pipeline commissioning delayed to February 1, 2027, instead of August 2026. 🔹 Reason: New Mexico authorities denied laying pipes through state lands due to environmental concerns. 🔹 2.5 GW power supply via Bloom Energy fuel cells is at risk.