Kyiv City State Administration (KMDA) has confirmed that the construction schedule for the first phase of the metro line to the Vynohradar residential area remains unchanged. According to the press service of the capital's administration, the main structures of the Mostytska and Varshavska stations are planned to be completed in 2027, while the full implementation of the entire project is scheduled until 2035. Work at the construction sites, according to officials, is proceeding as normal.
Three phases and the 2035 horizon
KMDA explained that the 2035 deadline, specified in Kyiv's updated Unified Project Portfolio of Public Investments (which launches on January 1, 2027), refers not to the two stations currently under construction, but to the entire complex of works. According to the feasibility study, the Vynohradar metro project consists of three phases: the first is the construction of Mostytska and Varshavska stations, the second is another station with a branch, and the third consists of two commissioning complexes including an additional metro station and an electric depot.
Work on European Union Avenue
One of the priority areas currently is the European Union Avenue section. There, specialists are completing the relocation of water and heat supply networks, gas pipelines, power and communication cable lines, as well as installing storm sewer and drainage systems. In areas where utility relocation is already complete, builders have begun restoring the roadway and sidewalks. These work is being carried out in an enhanced mode to restore traffic on the avenue as quickly as possible.
War factors in long-term planning
The city authorities emphasized that when long-term planning for such a large-scale infrastructure project, it is necessary to take into account security factors as well as economic constraints associated with the full-scale war. That is why, according to KMDA's logic, the general implementation horizon has been stretched to 2035, while the key structures of the first phase should be ready as early as 2027.
Context: other changes in Kyiv transport
The announcement regarding the Vynohradar metro timeline came against the backdrop of several other changes in the capital's transport operations. On November 21, Kyiv temporarily restricted access to one of the lobbies of the Khreshchatyk metro station due to a public holiday. In addition, the frequency of Kyiv Ring Express trains between the left and right banks was increased: from November 18 to 20, 16 additional trains ran during morning and evening rush hours for passenger convenience.