At the ZiO-Podolsk plant in the Moscow region, the manufacturing of the second steam generator for the MBIR research reactor (Multipurpose Fast Research Reactor) has been completed. The final batch of equipment has already been shipped to the SSC RIAR construction site in the Ulyanovsk region. According to the provided materials, the first steam generator was delivered to the site back in October, which marks the phased delivery of the facility’s key heat exchange equipment.

Two Reverse-Type Units Instead of a Classic Scheme

The MBIR design includes two reverse-type steam generators. Their construction differs significantly from the equipment used in nuclear power plants with VVER reactors. Each unit consists of three modules, which helps reduce the space required for placement within the reactor installation. This compact layout is essential for a research facility where every meter of the reactor hall is optimized for experimental equipment.

Experience Proven Since 1969

The technological solution is based on the design of the steam generator of the BOR-60 reactor, which has been in operation at the RIAR site since 1969. In reverse-type units, the sodium coolant passes inside the heat exchanger tubes, while water and superheated steam circulate in the shell-side space. Years of operation of the BOR-60, according to the developers, have confirmed the reliability of this scheme, which allowed it to be transferred to the new installation.

Why MBIR Is Needed

MBIR is being built to conduct research in the field of reactor technologies, study material behavior under extreme conditions, and develop advanced nuclear power installations. The reactor will also allow for tests related to closing the nuclear fuel cycle and the development of two-component nuclear energy. Thus, the installation is positioned not as an electricity source, but as a scientific platform where solutions for the next generation of reactors are being developed.

Project Within the National Program

The project is being implemented by Rosatom as part of the national project "New Atomic and Energy Technologies." It is expected that the scientific facility will become one of the key sites for research necessary for creating fourth-generation reactors. The delivery of both steam generators to the SSC RIAR site is a notable milestone in the assembly and preparation of MBIR for commissioning works.