Accumulated debt to renewable electricity producers in Ukraine is approaching the 15 billion UAH mark, according to experts. Vladimir Omelchenko, Director of Energy Programs at the Razumkov Center, stated that this dynamic undermines investor confidence and calls into question plans to build new generating capacities, including the previously announced 5 GW of maneuverable generation. This is reported by RBC-Ukraine with reference to the expert's statement on Facebook.
Debt Scale and Payment Chain
According to Omelchenko, investors in renewable energy built power plants, took out loans, and invested their own funds, counting on the state-guaranteed purchase of electricity at the 'green' tariff. However, they are now forced to wait months for payment for already produced electricity. The expert described the mechanism of debt propagation: "Ukrenergo's debts turn into 'Guaranteed Buyer's' debts, and subsequently into arrears to producers." Thus, non-payments at one level of the chain are passed to the next until they reach the end investors.
Investor Confidence and the 5 GW Plan
The state declares the need to build new maneuverable generation, including the previously announced 5 GW of capacity, but, according to Omelchenko, it has still not ensured full settlement with companies that have already invested in the Ukrainian energy sector. "How does the state intend to convince investors to build new power plants if it cannot fully settle with those who have already invested money in Ukrainian energy?" the expert noted. He emphasized that to attract investment in gas generation, solar and wind power plants, and energy storage systems, financial obligations to existing investors must first be met: "In my opinion, the best signal for future investors is paying off the debts to current ones."
Transmission Tariff for 2027 as an Additional Risk
As a separate risk factor for debt accumulation, Omelchenko pointed to the NEURC-proposed electricity transmission tariff for 2027 of 914.02 UAH/MWh, which is 1.6% lower than the current level. At the same time, the economically justified need calculated by Ukrenergo is 964.92 UAH/MWh. The gap between the level proposed by the regulator and the grid operator's calculation, according to the expert, creates additional pressure on the sector's financial stability.
Partial Payments and the Balancing Market Issue
Against the backdrop of total debt, certain payments are still being made but do not cover the full amount. According to the press service of the 'Guaranteed Buyer' JSC, the company fully settled with renewable energy producers for May 2026 by transferring 598.1 million UAH on November 2, and for July, the payment level is 75.01% after a payout of 124.6 million UAH; the total amount of these payments was 722.7 million UAH. In parallel, Serhiy Isachenko, CEO of Centrenergo JSC, previously reported that Ukrenergo's debt to the company for work on the balancing market is about 1.5 billion UAH, forcing the operator to balance between participating in this segment and selling electricity under bilateral contracts with more predictable revenues.
Demands to the State
Andriy Gerus, Chairman of the Verkhovna Rada Committee on Energy and Housing and Utility Services, previously stated that the state's primary task should be to stop the accumulation of new debts in the balancing market, as directing funds to repay arrears yields no results while non-payments continue to rise. Together, these statements indicate that, according to experts, without a systemic solution to the settlement problem, investor confidence and the implementation of plans to increase generating capacities remain at risk.